Proj Overview

Project Overview

When engineers designed the new Rich Street Bridge in Columbus, Ohio, they knew the structure had to do more than just offer cars and pedestrians a way across the river. The bridge was going to be a centerpiece for the city's thriving downtown riverfront, and a venue for festivals and community events.

"The owner wanted an iconic design that fit the style of the city," says John Shanks, project manager with Burgess and Niple, the engineer of record for the project.

The new structure would replace a historic but structurally deficient concrete spandrel-filled arch bridge, but it would be built on a new alignment slightly farther downstream.

Originally, the engineers envisioned a cast-in-place concrete ribbon arch bridge; however, midway through the design process, the engineer and architect were challenged to lower the overall cost of the project and shorten the construction time frame. "We determined that a precast concrete bridge was the only solution that would meet those project goals," Shanks says. "It allowed for greater speed and efficiency of construction, it was a lower-cost option, and it had greater expected durability than cast-in-place concrete."

Precast Solution

The new design is a 562 ft (171 m) modern rib arch bridge with semi-lightweight precast, post-tensioned concrete arch ribs. Using lightweight precast concrete arch ribs instead of the cast-in-place arch plates decreased the construction time and allowed for a minimal number of field segments, which were precast locally and transported via truck to the site.

The alignment was adjusted to make the bridge completely symmetrical, which allowed the 12 precast concrete elements that make up the varying span arches to be cast in one adjustable form, which saved both time and money. Bridge apex and beam segments also were designed to each be fabricated using one multiuse adjustable form. All post-tensioning strand-end anchorages were arranged to be concealed and terminate above flood level for added durability. The change to precast concrete ultimately shortened construction by seven months and reduced estimated project costs by $10 million.

The use of precast concrete also provided distinct advantages when incorporating bridge aesthetics, Shanks says. The modern arch structure uses precast concrete beam, arch rib, and arch apex segments stitched together with a combination of prestressing and field post-tensioning to create a fully continuous frame, eliminating intermediate expansion joints and spandrel columns, to allow for a slender open design that provides clear views of the water and city skyline. To create additional drama, architectural lighting was installed both above and below the bridge deck to light up the structure at night, creating a dazzling display that reflects off the river.

The new bridge has such widespread appeal that it has become the postcard shot for the city and regularly shows up as the backdrop for newscasts, newspapers, and tourism materials, Shanks says. "The use of semi-lightweight precast concrete, field-spliced post-tensioning, and a minimal number of efficiently tailored segments helps advance the boundaries of what can be achieved with precast concrete, melding aesthetic, durable, and economical bridge design."

 

Awards_
2014 PCI Design AwardsBest Bridge with a Main Span from 76 to 149 feet
2014 PCI Design AwardsDesign Award Special Award: All-Precast Concrete Solution
Project Team

Owner

Ohio Department of Transportation District 6

Client

City of Columbus, Department of Public Service

Architect

Bridgescape LLC

Engineer of Record and Precast Concrete Specialty Engineer

Burgess and Niple, Inc

Structural Engineer

Leonhardt, Andrä und Partner

Precaster

Prestress Services Industries, LLC

Contractor

Kokosing Construction Co., Inc

Photo Credit

Randall Lee Schieber Photography

Key Project Attributes

  • The efficiency of precast shaved 7 months off of the production schedule
  • Use of precast reduced project cost by $10 million 
  • Arch apex segments were stitched together with a combination of prestressing and field post-tensioning
  • Versatility of precast allowed for a beautiful design that is now use as the postcard shot for the city

Project/Precast Scope

  • Project Cost: $30,533,000
  • Bridge Length: 562 ft. (171 m)
  • 12 precast elements make up the span arches