Proj Overview

Project Overview

Providing an uncommon twist on the traditional hostel required an innovative approach to its architecture. Designers achieved this goal by using an all–precast concrete structural solution consisting of load-bearing wall panels and hollow-core slabs for the ceiling/second floor. The structural envelope played a key role in the facility’s ability to target LEED platinum certification, making it the first hostel to reach that level.

The precast concrete insulated sandwich wall panels were left exposed on the interior and feature a broom finish. Interior walls feature smooth drywall framing and were painted in bright colors to contrast with the exterior walls. Adding to the modern industrial aesthetic, the first floor consists of a solid concrete slab, while the second features a 1 in. (25 mm) cast-in-place-concrete floor over the hollow-core slabs. This created a quiet, sturdy structure on which guests frequently comment.

Precast Solution

The precast concrete panels were chosen because they were cost effective, were quick to erect, and offered high-quality finishes. Also factoring into the specification were life-cycle costs and maintenance. The 12 in. (300 mm) thick panels included 4 in. (100 mm) of expanded polystyrene insulation between two wythes of concrete tied together with carbon-fiber shear grid. This provided an R-value of 20. Some 26 panels, typically measuring 12 ft (3.7 m) wide and 25 ft (7.6 m) tall, were erected in only three days.

The panels’ thermal mass and insulation helped create a design that was more than 50% more efficient than a standard building. They also helped create sound-isolating interior spaces. This was important because the building includes a garden and pavilion, often used for nighttime events that are adjacent to private rooms. That adjacency required exceptional sound control.

Offsite fabrication of the panels allowed site work and other preparation to precede concurrent with panel manufacture, allowing the building to be erected quickly and prepared for interior trades. Construction took only six months, with the precast concrete structure erected only two months after groundbreaking.

 

Awards_
2012 PCI Design AwardsBuilding Award: Best Hotel
Project Team

Architect

River Street Architecture, Chattanooga, TN 

Engineer

Kinnaman Consulting, Chattanooga, TN 

General Contractor

Collier Construction, Chattanooga, TN 

Owner

The Crash Pad LLC, Chattanooga, TN 

Precaster

Metromont Precast Building Solutions, Hiram, GA 

Precast Specialty Engineer

PTAC Consulting Engineers Inc., Pensacola, FL

Key Project Attributes

  • Precast concrete panels were chosen because they are cost effective, were quick to erect, and offered high-quality finishes.
  • The panels’ thermal mass and insulation created a design that was more than 50% more efficient than a standard building.
  • Offsite fabrication of the panels allowed site work and other preparation to proceed concurrent with panel manufacture

Project/Precast Scope

  • Project size: 4320 ft2 (401 m2)
  • Project cost: $1.1 million\
  • 26 panels, measuring 12 ft (3.7 m) wide and 25 ft (7.6 m) tall, were erected in only three days.