Proj Overview

Project Overview

The original Skilton Road Bridge in Watertown, Conn., is one of those classic stone structures that you find in small east coast towns. Constructed in 1865, the stacked cobbled stones and classic arch are typical in these historical structures.

But by 2011, this fairy tale structure was in desperate need of repairs. Despite efforts to reinforce the arch and walls of the historic landmark, the stone masonry at the west abutment was beginning to fail.

In response, the Connecticut Department of Transportation (CDOT) launched a rehabilitation project for the bridge that was jointly funded by the CDOT and the town of Watertown. The new design had to bring the bridge up to code and extend its life, without sacrificing the history character of the original structure. It also had to be expanded from one lane to two in order to secure CDOT Local Bridge Program funding, and include a new sidewalk to increase safety for pedestrians.

The designers considered several potential schemes to rehabilitate the structure, and ultimately decided to install a new superstructure consisting of precast, prestressed concrete slabs that would bear directly on the existing arch bridge, thus preserving and protecting the entire historic structure. “The use of prestressed, precast concrete beams enabled the bridge to be widened while minimizing the impact on the existing bridge,” says William Andres, associate with Tata and Howard, the engineer for the project.

A key advantage to utilizing precast, prestressed concrete on this project was that the precast concrete slabs were cast while demolition and construction of new beam seats were being completed, which shortened the project timeline and minimized disruption. It also reduced the time needed to detour traffic around the construction site, and eliminated the need for scaffolding and formwork. “That made it made it less expensive than a cast-in-place design,” Andres says.

Precast Solution

The precast concrete slabs were prestressed to resist the required construction loads and to carry the required in-place design loads. Instead of orienting them in the normal longitudinal direction, the slabs were installed transverse to the roadway, extending out roughly 5 ft beyond the existing stone masonry walls. Installation of the slabs took just 1 day.

“Typically, these types of precast, prestressed slabs are transversely connected using grouted shear keys with post-tensioning tendons to ensure that the slabs deflect together under load,” Andres says. However, due to the vertical geometry of this site, post-tensioning was ruled out because of concerns about alignment and deformations in the slabs during posttensioning.

A mildly reinforced, cast-in-place concrete connection was adopted instead. “This provided the ability to transfer full shear and moment between slabs while allowing the each slab to rotate as necessary to follow the curvature of the vertical geometry.”

To ensure durability and decrease maintenance, a waterproof membrane was placed over the precast concrete beams and new storm drains were installed to protect the existing stone masonry from water damage. “The end result was a monolithic high-performance precast, prestressed concrete slab system that spans from start to end of bridge, Andres says. “It produced an excellent riding surface while protecting the stone arch below.”

 

Awards_
2016 PCI Design AwardsDesign Awards Transportation: Best Rehabilitated Bridge
Project Team

Engineer of Record

VB Technologies Corp., Rocky Hill, Conn. 

Contractor

Black & Warner Construction Company, Unionville, Conn. 

Owner

Town of Watertown, Watertown, Conn. 

Precast Producer

Oldcastle Precast, Rehoboth, Mass. 

Precast Concrete Specialty Engineer

Eriksson Technologies, Tampa, Fla.

Key Project Attributes

  • The use of precast, prestressed concrete slabs allowed designers to expand and repair an aging masonry bridge while maintaining its aesthetic appeal.
  • Precast concrete slabs were set in 1 day, eliminating the need to construct staging and formwork on site.
  • Waterproofing and storm drains will prevent damage from winter freezing-and-thawing cycles.

Project/Precast Scope

  • Project Cost: $700,000.00
  • Bridge Length: 102 ft
  • Repair historic masonry bridge, adding a second lane and sidewalk while maintaining existing stone arch and walls.
  • Project components featured 12 precast concrete slabs.
  • The precast, prestressed concrete superstructure bears directly on the existing arch bridge, thus preserving the entire historic structure.