Proj Overview

Project Overview

Time was of the essence for this project to build a new pedestrian bridge that could safely carry people from a parking garage to the hospital at Loma Linda University in California. The owners did not want to disrupt traffic any more than was necessary on the busy campus, so they went with a precast concrete solution. By choosing a precast concrete, the contractors were able to limit closure of the street to just one day on order to place the new 8 ft (2.4 m) wide pedestrian walkway—emblazoned with the words “Loma Linda University Health”—over Campus Street, which serves as the entrance to the Loma Linda hospital emergency room.

Precast Solution

The bridge features a series of precast concrete pieces, including 26 precast concrete bridge panels and two 187,900 pounds (835.8 kN) prestressed bridge girders to complete the 120 feet (37 m) long bridge. In addition, each girder had 30 posttensioned cables. Delivery of the completed precast concrete pieces was within 30 business days of the signed approved shop drawings, and installation of the precast concrete bridge girders and panels took just one day.

Had the owner chosen a cast-in-place concrete solution, the project would likely have disrupted traffic for more than two months, and it would have been far more costly, the precast concrete producer reports. Instead, thanks to the creative use of precast concrete, there was minimal impact to patients and hospital staff; there was virtually no down time among the onsite labor; and it increased the safety of everyone in and around the construction area.

 

Awards_
2015 PCI Design AwardsNon-highway Bridge Honorable Mention
Project Team

Owner

Loma Linda University Health, Loma Linda, Calif. 

Engineer

Culp & Tanner, Chico, Calif. 

General Contractor

Bomel Construction Co., Anaheim, Calif. 

Precaster and Precast Specialty Engineer

StructureCast, Bakersfield, Calif. 

Photo Credit

StructureCast

Key Project Attributes

  • The use of precast concrete limited closure of the busy hospital entrance to a single day.
  • By casting the pieces off-site, there was minimal impact to the jobsite.
  • The use of precast concrete decreased downtime and increased the safety of the traffic around the construction area.

Project/Precast Scope

  • Precast concrete components: 26 precast concrete bridge panels and two 187,900 pounds (835.8 kN) prestressed concrete bridge girders.
  • Total cost of precast concrete: $300,000
  • Precast concrete erection completed in just two days.
  • Project cost: $1.5 million