Engineer
PB, Lawrenceville, N.J.
Contractor
Agate Construction Co., Ocean View, N.J.
Owner
New Jersey Turnpike Authority, Woodbridge, N.J.
Precaster
Precast Systems, Allentown, N.J.
Precast Specialty Engineer
Freyssinet, Sterling, Va.
Key Project Attributes
- Precast concrete design cost $5.1 million less than a comparable steel option.
- Resulted in high performance structure
- Reduced footprint within the waterway
- Resiliency of precast was important for this structure due to its location
Project/Precast Scope
- Features 1,230 feet (375 m) of precast concrete
- Span lengths were maximized to 220 feet (67 m)
- Three 8 feet (2.4 m) diameter drill shafts that extend over 150 feet (46 m)
- Seven prestressed concrete spliced girders sitting on pier caps
- Took six months to be completed
|