Proj Overview

Project Overview

In 2017, St. Joseph’s Hospital in Tampa, Florida, broke ground on an expansion project that would bring greater accessibility to patients and become a beautiful new addition to the community. At the core of the project was a six-story tower featuring a beautiful covered entry, 90 new private patient rooms, and a pedestrian bridge to the Women’s Hospital across the street.

When designing the new addition, the architects wanted the organic geometry of the building to reflect the human body while softening the perception of the typical hospital building. They relied on precast concrete to achieve that vision in a durable and cost-effective design.

The addition features a three-dimensional, prefabricated precast concrete skin that “pushes the boundaries between design and manufacturing,” says Noble Levesque, senior project manager for Gate Precast. The defining element of the architecture are the 25-ft-tall precast concrete structural V-shaped columns at the first floor.

The rest of the design includes multiple shapes, including double C-shaped panels, curved panels, a conical base, and parapet panels. “A triangular window with a rounded corner with a deep recess became a signature feature of the entire building,” says Yuri Jukarev, principal of J & M Structural Engineers. “This portion of the building required specific attention during the design stage and resulted in unique design challenges.”

Dimensional control was paramount

The corners were especially challenging, Levesque says. To be sure they could meet the exact specifications, the precast team created a mock-up to identify any fit issues and then they measured, remodeled, rebuilt, repoured, and recast the final pieces. “The effort to hold dimensional control was paramount, and the craftsmanship is in full display,” he says.

Bulky parapet panels had to be designed as freestanding elements at the locations where a panel joint was located at the roof level. The three-dimensional level panels along the south elevation also had a significant negative slope and were designed with leaning bearing connections.

Because construction had to be accomplished while the hospital was fully operational, the project required tight coordination of multiple disciplines within confined site restrictions, with access limited to a narrow strip of land. To accommodate these constraints, the structure was erected using a single tower crane shared by the concrete, structural steel, precast concrete, and glass and glazing subcontractors. This resulted in some trade partners working night shifts so the work could continuously flow around the perimeter of the building.

The work progressed in a counterclockwise direction by elevation. It started with the erection of miscellaneous structural steel supports, which were immediately followed by the precast concrete elements and then the glass and glazing units. As each elevation was completed, the precast concrete was punched due to limited accessibility.

The team’s careful collaboration was achieved through daily communication and work plan meetings led by the installing supervisors. This ensured that the project was completed safely without risk to the operational facility or other employees. The project was completed in 2019, and the facility is now providing expanded care to the Tampa community.

 

Awards_
2022 PCI Design AwardsBest Healthcare and Medical Building
Project Team

Owner:

Baycare Health System, Tampa, Fla.

PCI-Certified Precast Concrete Producer:

GATE Precast Company, Kissimmee, Fla.

Precast Concrete Specialty Engineer:

J & M Structural Engineers, Kissimmee, Fla.

Architect:

HOK, Tampa, Fla.

Engineer of Record:

Walter P Moore, Tampa, Fla.

General Contractor:

Robins & Morton, Orlando, Fla.

PCI-Certified Erector:

WW Gay Mechanical Contractors, Inc., Jacksonville, Fla.

Project Cost:

$102 million

Project Size:

156,000 ft²

Key Project Attributes

  • Triangular windows with a deep recess are a signature feature of the building.
  • A single tower crane was shared by precast concrete, structural steel, and glass trades.

Project/Precast Scope

  • Create a precast concrete exterior and entryway for a six-story hospital addition.
  • The project included 316 architectural precast concrete pieces.
  • Installation was completed in two months.