PROJECT OVERVIEW
During a multi-year assessment of the circa-1974 museum, the owner identified several issues to be addressed. Most significantly, the precast panels on the unique circular exterior were no longer viable, as they had compromised lateral attachments at many locations. And because the original structure had been built in a fast-tracked manner, there were numerous imperfections in its original construction.
The initial project focused solely on the exterior 44,400 square feet of precast recladding with a future contract to be awarded for the full revitalization of the interior (60,000 square feet). The corrections also included the installation of new waterproofing and insulation layers between the precast walls and existing structure, which in turn enlarged the façade by 3 inches in radius.
INNOVATIVE PRECAST
SOLUTIONS
The team incorporated the use of laser scans and data-point modeling, as well as traditional surveying methods, to determine the existing conditions of the underlying structure. The precaster, designed and implemented an innovative system for hanging the new panels that would accommodate the existing conditions, meet blast-load requirements, while also dealing with minimal access behind the panels.
In order to meet the historical preservation requirements to match the appearance of the original panels from when the museum was first constructed, Millennium Pink granite was sourced from the quarry that originally provided the stone. No area in the panel could be larger than a quarter without exposed aggregate, and there were limits on the amount of naturally occurring black and white rocks that could be exposed.
Following the precaster’s internal QC inspections at its manufacturing facility, the client performed an additional 30-point inspection of the panels upon their arrival at the site. The owner’s representative, general contractor, and architect individually inspected every panel from 10 feet. Procore was used to track and document inspections and the resolution of any concerns. By project’s end, the team had erected 673 pieces wall panels, along with numerous blended plugs and filler pieces wherever access holes were needed to complete connections.
All the precast panel restoration work was performed as the museum remained open. The challenging, and often complex job, was completed on time and on budget, bringing the iconic museum back to its original grandeur and provided it with a significantly longer service life. |